Gov. Justice celebrates completion of I-70 bridge project in Wheeling

January 29th, 2023 by WCBC Radio

 

WHEELING, WV – Gov. Jim Justice and leaders from the West Virginia Department of Transportation held an event today to officially commemorate the completion of the I-70 Bridge Project in Wheeling.

The project, which rehabilitated or replaced 26 bridges and ramps along a seven-mile stretch of I-70 in Wheeling, was the largest project undertaken under Gov. Justice’s Roads to Prosperity program when bid in 2019. Final cost of the project is $221,034,932.55.

"Everyone said that this would be impossible, and it was going to take forever, and the traffic was going to be crazy, and everything under the sun," Gov. Justice said. "But lots and lots of people pulled the rope, did they not? Whether it was our great Jimmy Wristen, the Department of Transportation, Randy Damron, all the contractors, all the people that made this all happen, all the great city people, the workers, and all of our officials, we're so good in this state when we unleash us."

 

 

“We really put out the full court press with all the stakeholders up there – the emergency responders, the local government entities, even the businesses and hospitals,” said Secretary of Transportation Jimmy Wriston, P.E. “We needed everyone to know exactly what we were going to do and how we were going to do it, so we could still get traffic safely through this monstrous, 26-bridge project.

“We needed to have a safe work zone out there that the public could still traverse, and we did that,” Wriston said. “Home run.”
 
Swank Construction Company was awarded the construction contract in August 2019 and began construction in September. Work ranged from simple redecking of existing bridges to complete replacement.
 
The largest impact on traffic was total replacement of the twin Fulton bridges, which required the complete closure of portions of I-70 for nine months at a time. Work on the westbound span was done in 2020, while work on the eastbound span was done in 2021.

Bridges and ramps west of the Wheeling Tunnel were painted blue at the request of the city of Wheeling, while spans east of the tunnel received a fresh coat of gray paint.

 

 

While major construction on the project is complete, painting below some of the bridges and other minor work will continue into 2023.
 
"We knew that this project was going to be difficult from the beginning due to the amount of work required and the volume of traffic on I-70,” said West Virginia Division of Highways (WVDOH) District 6 Engineer Tony Clark, P.E. “Due to the Roads to Prosperity bond program, we were able to perform this large amount of needed bridge repairs and replacements under one contract in a relatively short amount of time rather than dragging the work out over several years and multiple contracts.”